PVEDI provided remedial investigation, geophysical survey, and soil and groundwater sampling services. The field work was separated into two phases: the first phase was completed between August 16, 2021, and September 24, 2021 that included the completion of fifteen soil borings. The second phase was completed between January 17, 2022 and March 4, 2022 that included the completion of twelve soil borings, installation of ten monitoring wells, and excavation of two test pits.